Road resurfacing work in Haverfordwest is due to restart this week after a break for Easter.

Following earlier resurfacing of Sydney Rees Way, workmen will start planing the Withybush Hospital section on Thursday, 9th April.

Planing work will continue through Thursday evening and Friday and is currently expected to be completed on Friday evening.

Withybush roundabout itself will be resurfaced on Saturday evening, with the remaining resurfacing work recommencing on Monday.

Road markings will be repainted afterwards and it is hoped that the project will be fully completed by 22nd April.

All work will be carried out under traffic management and in order to minimise delays motorists are advised to follow the signed diversions.

The contractors are GD Harries and Sons, Templeton.